Added work
"While you're here…"The client asks for an extra room, an extra outlet, a second coat. The most common change order, and the most often left unwritten.
“While you're here, could you also…?” Those five words quietly eat contractor profits on almost every remodel. A signed change order puts added work, price changes and extra days in writing before you lift a tool—so invoice day brings zero surprises.
Any time the job you are doing stops matching the job you priced, the gap belongs in a change order.
The client asks for an extra room, an extra outlet, a second coat. The most common change order, and the most often left unwritten.
The client decides to keep the old cabinets or to do the painting themselves. A change order credits the lines taken out.
The tile chosen is out of stock, or the client upgrades the fixtures. The new product, its price and any delay go in writing.
Rot behind the drywall, old wiring, a leak under the floor. Photograph it, show the client, and price the repair before doing it.
A moved wall, a different layout, a new finish. Even when the price barely moves, the schedule often does.
Work paused at the client's request, or access to the site delayed. If it costs you days or a return trip, it belongs in a change order.
Six steps, done before the extra work starts. Most of them take a minute on site.
Before any extra work, write what changes and why, in words the client will recognize later: "Replace rotten subfloor in bathroom, approx. 40 sq ft."
Name the estimate or contract it changes by its number and date, so the two documents read as one.
Labor and materials as separate lines, added work as positive lines, removed work as negative lines.
Original price, this change, new job total. The client should see in one line where the job now stands.
If the change adds days, say how many. A later finish agreed in writing is not a late finish.
The client signs and dates it before you start the extra work. Keep a copy, and give one to the client.
| Field | Example |
|---|---|
| Change order number | CO-0002 |
| Original estimate or contract | Estimate EST-0014, signed Sep 2 |
| Description of the change | Replace rotten subfloor in bathroom |
| Reason | Damage found after removing old tile |
| Lines added | Subfloor, 40 sq ft × $9.00; labor, 4 hrs × $65.00 |
| Lines removed | Floor leveling compound, −$80.00 |
| Price of this change | +$540.00 |
| New job total | $6,290.00 (was $5,750.00) |
| Schedule impact | +1 day |
| Signatures and date | Client and contractor, Sep 9 |
"Change order" is the usual term in the United States and Canada. In the UK, building contracts usually speak of a variation, and in other contracts of an amendment. The names differ; the principle is the same: a written, agreed change to what was signed.
When the change is so large that the original job barely survives, a new estimate is clearer than a long change order. A useful test: if the change order would replace most lines of the estimate, start a new estimate and close the old one.
Price a change order the way you priced the estimate: the same hourly rates, the same material margins, the same units. A client who compares the two documents should find the same logic in both. Then add what the change really costs you beyond the work itself: a return trip, materials ordered in a hurry, disposal, a day added to the schedule.
For removed work, credit what you will no longer spend, not necessarily the full line of the estimate. Materials already bought, or a crew already booked, may be a cost you still carry; say so on the change order instead of absorbing it in silence. And if a change only moves the schedule, it still deserves a change order with a price of zero: the new dates are what matter.
In BillSmith, change orders attach directly to an accepted estimate. Tap Add change order, list added work (or negative lines for removed items), and the app assigns the next CO number while updating the revised job total right in front of both of you.
Hand over your phone so the client signs with a finger before you start the extra work. When the job wraps, tap Convert to invoice and every accepted change order flows straight into the final bill without retyping—included on every plan, with or without Pro. Need to sharpen the initial quote too? Read how to write an estimate.
Your client's signature is the essential one—it confirms they approved the scope change and new price before work began. Usually you sign too, and larger jobs may also include a project manager or architect.
Yes. If a client removes part of the original scope—like keeping existing cabinets—a change order logs those removed items as negative amounts and adjusts the total downward cleanly.
If it adds cost or days to the schedule, yes. Three small verbal favors easily turn into a $600 argument at final billing. If a tweak costs nothing and changes no dates, a quick note is enough.
A change order modifies an existing estimate or contract (scope, price or timeline). A work order documents work performed and materials used during a visit—often signed off at completion and billed directly.
Yes—US and Canadian contractors call it a change order, while UK building contracts usually call it a variation. Both mean a signed written adjustment to the agreed scope and price.
Add a change order right onto an accepted estimate in BillSmith, have your client sign on your screen, and carry every approved extra straight into the final invoice.
iPhone & Android · No account · No ads · Zero commission