What is a change order—and why it protects your margin

“While you're here, could you also…?” Those five words quietly eat contractor profits on almost every remodel. A signed change order puts added work, price changes and extra days in writing before you lift a tool—so invoice day brings zero surprises.

When to write one

Six situations that call for a change order

Any time the job you are doing stops matching the job you priced, the gap belongs in a change order.

Added work

"While you're here…"

The client asks for an extra room, an extra outlet, a second coat. The most common change order, and the most often left unwritten.

Price goes upClient request

Removed work

Scope reduced

The client decides to keep the old cabinets or to do the painting themselves. A change order credits the lines taken out.

Price goes downClient request

Material substitution

Different product

The tile chosen is out of stock, or the client upgrades the fixtures. The new product, its price and any delay go in writing.

Price up or downMaterials

Hidden conditions

Found once opened

Rot behind the drywall, old wiring, a leak under the floor. Photograph it, show the client, and price the repair before doing it.

UnforeseenTake photos

Design change

New idea mid-job

A moved wall, a different layout, a new finish. Even when the price barely moves, the schedule often does.

Scope and timeClient request

Schedule change

Dates move

Work paused at the client's request, or access to the site delayed. If it costs you days or a return trip, it belongs in a change order.

TimeReturn trips

How to write a change order

Six steps, done before the extra work starts. Most of them take a minute on site.

Stop and describe

Before any extra work, write what changes and why, in words the client will recognize later: "Replace rotten subfloor in bathroom, approx. 40 sq ft."

Reference the original

Name the estimate or contract it changes by its number and date, so the two documents read as one.

Price each change

Labor and materials as separate lines, added work as positive lines, removed work as negative lines.

Show the new total

Original price, this change, new job total. The client should see in one line where the job now stands.

Note the schedule

If the change adds days, say how many. A later finish agreed in writing is not a late finish.

Get it signed first

The client signs and dates it before you start the extra work. Keep a copy, and give one to the client.

What a change order includes, with an example
FieldExample
Change order numberCO-0002
Original estimate or contractEstimate EST-0014, signed Sep 2
Description of the changeReplace rotten subfloor in bathroom
ReasonDamage found after removing old tile
Lines addedSubfloor, 40 sq ft × $9.00; labor, 4 hrs × $65.00
Lines removedFloor leveling compound, −$80.00
Price of this change+$540.00
New job total$6,290.00 (was $5,750.00)
Schedule impact+1 day
Signatures and dateClient and contractor, Sep 9

Change order, variation or new estimate?

"Change order" is the usual term in the United States and Canada. In the UK, building contracts usually speak of a variation, and in other contracts of an amendment. The names differ; the principle is the same: a written, agreed change to what was signed.

When the change is so large that the original job barely survives, a new estimate is clearer than a long change order. A useful test: if the change order would replace most lines of the estimate, start a new estimate and close the old one.

How to price a change order

Price a change order the way you priced the estimate: the same hourly rates, the same material margins, the same units. A client who compares the two documents should find the same logic in both. Then add what the change really costs you beyond the work itself: a return trip, materials ordered in a hurry, disposal, a day added to the schedule.

For removed work, credit what you will no longer spend, not necessarily the full line of the estimate. Materials already bought, or a crew already booked, may be a cost you still carry; say so on the change order instead of absorbing it in silence. And if a change only moves the schedule, it still deserves a change order with a price of zero: the new dates are what matter.

In short

  • Write a change order whenever the price, the scope or the schedule moves.
  • Reference the original estimate or contract by its number.
  • Show the price of the change and the new job total.
  • Get the client's signature before the extra work starts.
  • Carry every signed change order into the final invoice.

Capture extra work on the spot with BillSmith

In BillSmith, change orders attach directly to an accepted estimate. Tap Add change order, list added work (or negative lines for removed items), and the app assigns the next CO number while updating the revised job total right in front of both of you.

Hand over your phone so the client signs with a finger before you start the extra work. When the job wraps, tap Convert to invoice and every accepted change order flows straight into the final bill without retyping—included on every plan, with or without Pro. Need to sharpen the initial quote too? Read how to write an estimate.

FAQ

Change order FAQ

Who needs to sign a change order?

Your client's signature is the essential one—it confirms they approved the scope change and new price before work began. Usually you sign too, and larger jobs may also include a project manager or architect.

Can a change order lower the job total?

Yes. If a client removes part of the original scope—like keeping existing cabinets—a change order logs those removed items as negative amounts and adjusts the total downward cleanly.

Do I really need a change order for small add-ons?

If it adds cost or days to the schedule, yes. Three small verbal favors easily turn into a $600 argument at final billing. If a tweak costs nothing and changes no dates, a quick note is enough.

How is a change order different from a work order?

A change order modifies an existing estimate or contract (scope, price or timeline). A work order documents work performed and materials used during a visit—often signed off at completion and billed directly.

Is a change order the same as a variation?

Yes—US and Canadian contractors call it a change order, while UK building contracts usually call it a variation. Both mean a signed written adjustment to the agreed scope and price.

Get extra work signed off before you start

Add a change order right onto an accepted estimate in BillSmith, have your client sign on your screen, and carry every approved extra straight into the final invoice.

iPhone & Android · No account · No ads · Zero commission

BillSmith app icon
Coming soon

BillSmith is almost here

BillSmith is on its way to the App Store and Google Play. Leave your email and we will send you one message on launch day, with the link for your phone.

Your phone

One email at launch, nothing else. We delete your address once it is sent. Privacy policy